Inside Climate News • 8/24/2026 – 8/25/2026
The Electric Reliability Council of Texas (ERCOT) announced that the audit of data centers, as requested by Governor Abbott, will be completed in December. The first group of large data centers seeking to connect to Texas’ grid will not proceed until mid-December, as ERCOT staff needs to review the first 300 projects, with 90 percent being data centers, in “Batch Zero” and conduct a community impact review.